Performance Management Guidelines
Intent
The following performance management guidelines assist project teams in gathering necessary information and coordinating the design, construction, and operations processes in order to ensure that each project successfully meets key performance criteria, including those of the B3 Guidelines. Successful implementation of appropriate processes, including integrative design, can minimize risk and improve outcomes.
Performance Management Guidelines | New Buildings | Renovations |
---|---|---|
P.1 Design and Construction Process | Required | Required |
P.2 Operations Process | Required | Required |
General Performance Management and Project Information:
The following information is collected in the Performance Management section of the B3 Guidelines Tracking Tool, under Section P.0:
Predesign:
- Project schedule
- Project budget
Design:
- Updated project schedule
- Updated project budget
- Building information – occupancy, building gross square footage, number of stories
Final Design:
- Updated project schedule
- Updated project budget
- Updated building information – occupancy, building gross square footage, number of stories
- Performance strategies used, including narrative
Closeout:
- Updated project schedule
- Actual project cost
- Updated building information – occupancy, building gross square footage, number of stories
- Updated performance strategies used, including narrative
Occupancy – Submitted annually for ten years:
- Updated building information – occupancy, building gross square footage, number of stories