Guidelines Home | v3.2r02 | v3.1 | v3.0 | v2.2 | Training | Documents | Previous Versions
Guideline P.1 Design and Construction Process
Intent
To support the compliance and outcome tracking process by facilitating the creation and communication of relevant project goals and information.
Required Performance Criteria
Guidelines are required for New Construction and Major Renovation projects.
- Develop an Owner’s Project Requirements (OPR) document, beginning at the Predesign or equivalent phase. This document is developed in coordination between the owner, commissioning authority, architect, engineer, and any other relevant stakeholders. A commissioning authority must be established at the Predesign phase to complete the early-phase goal setting. The OPR includes:
- A list of the authors who developed the document and assisted in early team kickoff and goal-setting meeting(s).
- All sections listed in Section 6, Appendix D of ASHRAE 202-2013.
- A preliminary SB 2030 Energy Standard, as created through the SB 2030 Energy Standard Tool.
- Regular updates and developments as the owner’s requirements change and project details become available.
- The requirement that trend data is able to be saved for major equipment for a minimum of two months if a building automation system is requested.
Projects that include less than 20,000 gsf of conditioned space may elect to complete the B3 Guidelines Small Buildings OPR to satisfy this guideline, using Appendix P-1a as a template. Projects must meet the B3 Guidelines requirements noted in this OPR/BoD template, and may use it to document compliance with Guidelines P.1A, P.1C, and the thermal comfort requirements of I.4B part 2.
- Develop a Commissioning Plan (Cx Plan) from the OPR with the assistance of the architect, engineer, commissioning authority, and owner. The Cx Plan shall follow Section 7 and Appendix E in ASHRAE 202-2013. The scope of commissioning shall follow the process outlined in Appendix P-1b1 and P-1b2 and include all of the following, if within project scope:
- Mechanical HVAC systems, including testing, adjusting, and balance.
- Energy (including renewable) systems.
- Power and electrical systems, including lighting and daylighting controls.
- Indoor air quality elements and systems.
Projects that include less than 20,000 gsf of conditioned space are only required to commission HVAC systems and lighting controls.
- Develop a Basis of Design document (BoD) from the OPR with the assistance of the architect, engineer, commissioning authority, and owner. The BoD shall follow Section 8 and Appendix F of ASHRAE 202-2013. Projects that include less than 20,000 gsf of conditioned space may submit a completed OPR/BoD template following Appendix P-1a to comply with this guideline.
- Develop a safety risk assessment of indoor air quality issues for projects that are attached to occupied buildings (“new construction” additions or “major renovations” only). Projects must submit a completed B3 Guidelines IAQ Safety Risk Assessment template to comply with this guideline, available as part of Appendix P-1e1.
- Develop indoor air quality procedures according to a Construction Air Quality Management Plan and Warranty Period Air Quality Management Plan templates, available in Appendix P-1e1 and P-1e2. These plans must address at a minimum the sections outlined in Appendix P-1e1 and Appendix P-1e2, although projects that include less than 20,000 gsf of conditioned space are only required to document and pursue a subset of the listed procedures. These are noted in the appendix.
Recommended Performance Criteria
- Assemble an appropriate stakeholder team that includes representation from every discipline involved in the project, including: the owner’s decision-making team, users, occupants, operations and maintenance representatives, at least one representative from the community, and at least one agency “client” or visitor representative. An owner representative and commissioning agent must also be included, if applicable. Members must make a commitment through post-occupancy.
- Facilitate planning/review workshops at key phases with all team members.
- In Predesign:
- Comprehensive planning workshop
- Programming workshop
- In Design:
- Conduct facility performance workshop within the first 2–3 weeks of the design phase.
- Convene a multidisciplinary team at least once per design phase for integrated progress review toward guidelines.
- Convene a stakeholder team for regularly integrated progress reviews. Stakeholder team to meet a minimum of once per phase.
- Convene general contractor and subcontractors for preconstruction kickoff meeting to review the B3 Guidelines goals and objectives.
- Discuss progress toward project outcomes during construction meetings.
- After occupancy:
- Convene facility operations manager, human resources manager, and others who offer cross-disciplinary points of view on facility operations for annual meetings to review operation practices, complaints, and building maintenance issues.
- In Predesign:
- Additional Commissioning Scope. Incorporate into the commissioning of the project one or more of the following:
- Plumbing Systems
- Interior materials
- Physical measurement of vibrations/acoustics/noise